Call: +55 27 99277-6120

Lifts completed fulfilling the motto: “Without safety there is no project”!

The assembly of 5 covering modules for the new wagon tipper warehouse was completed this weekend, involving a total of more than 300 tons of metal structure.

The work also included the removal of the entire metal roof, built in 1981, making it a major challenge to guarantee its structural integrity.

WHY DID EVERYTHING GO WELL, DESPITE THE DIFFICULT CONDITIONS?
🔹 Exhaustive field survey
🔹 Pre-weighing of loads
🔹 3D rigging plan, made specifically for each lift
🔹 Planning in advance
🔹 Relationship between designer, rental company, assembler, inspection and end customer
🔹 Trained and motivated team

SCOPE OF TechCon Engineering and Consulting
🔹 Execution of weighing for checking weight and CG
🔹 Structural design of the rocker and slings
🔹 Structural reinforcement project for the existing roof for lifting
🔹 3D rigging plans
🔹 Field supervision and consultancy during lifting

Assembly: Sigdo Koppers Brasil SKIC
Cranes and axis lines: Transdata Engenharia e Movimentação